Overview
This information sheet explains the additional information required to accompany an application for acceptance of a gas application that falls into one of the following categories:
- Has a total gas rate exceeding 3.8 gigajoules per hour.
- Has an operating pressure exceeding 200 kilopascals.
- Is being installed in a building exceeding 10 storeys above ground level.
This requirement is generally specified under section 73 of the Gas Safety Act 1997, and is specified in detail under Regulation 26 and Schedule 8 of the Gas Safety (Gas Installation) Regulations 2018.
The application for acceptance requires the Schedule 8 information because of the additional risks introduced into a gas installation by a high gas load, high pressure, or the installation being within a high rise building. The additional design and planning is required to ensure compliance and an acceptable safety outcome for the community.
If an applicant believes parts of Schedule 8 do not apply, then this should be stated in the application, including the reasons why. If additional information is required, Energy Safe Victoria will send a written request detailing what it is.
Schedule 8 information requirements
This table lists the additional information a Schedule 8 requires and provides additional detail to assist with sourcing the information.
Requirement | Description |
---|---|
Part 1 – Details of the gas installation, including drawings of: | |
a) The general arrangement of the consumer piping; and | A legible schematic (preferably in CAD format using the symbols in AS/NZS 5601.1:2022 appendix O). The drawings should include a title block with the installation address. |
b) The location of valves, pressure control regulators and other controls or devices installed within the piping; and c) The location of any gas meter (but not the gas company’s meter); and | The schematic must include:
|
d) Piping designed to safely discharge gas from safety or control devices; and | This is referring to the vent line design details and its termination point. |
e) Any associated electrical circuit diagrams | Where a device is electrically operated (like a gas solenoid, pressure proving system, or mechanical ventilation) the associated electrical schematic (or schematics) is required. For further requirements regarding mechanical ventilation refer to AS/NZS 5601.1:2022 clause 6.4.9. Note: hand drawn schematics are acceptable for installations of a less complex nature provided they are clear and legible. For example, a single run to a large hot water heater in a factory. |
Part 2 – Details of design, calculations, test and commissioning procedures, including: | |
a) Calculations of pressure loss | The design pressure drop must be nominated in the application. This requirement relates to pipe sizing and not to gas tightness testing.
AS/NZS 5601.1:2022 Appendix F provides guidance for pipe sizing and allowable pressure drop.
|
b) Testing for gas tightness | Stating in the application that this is the procedure being used satisfies this section of the Schedule, but you must also include the:
Installations outside the scope of Appendix E
|
c) Purging associated with commissioning or decommissioning piping | Use the purging procedure described in AS/NZS 5601.1:2022, Appendix D provides for pipe volumes up to 30 litres (0.03m3).
Installations outside the scope of Appendix D
|
d) Commissioning pressure control and other pipeline devices. | Provide details about the commissioning procedures for: • pressure control • other pipeline devices which may include over-pressure shut-off (OPSO) regulators, pressure proving solenoid valves, and gas boosters. |
Part 3 – Details of all control or other devices installed within the piping, including: | |
a) Manufacturer’s data sheets | Include the manufacturer’s data sheets/instructions with the application when installing control devices that may include regulators, gas pressure raising devices, pressure proving systems, or solenoids. |
b) Proposed setting of all adjustable devices. | Include the proposed settings (for example, the regulator inlet and outlet pressures, and the OPSO trip settings) when installing adjustable devices, which may include regulators, gas pressure raising devices, pressure proving systems, high and low gas pressure switches, and OPSOs. Ideally, include this information in the design drawing in Part 1. |
Date: 21/11/2024 4:55
The material in this print-out was accurate at the time of printing.
Reviewed